Forestation Project · Active · Phase 1 progress recorded · Phase 2 pending approval
Ulu Slim Forest Plantation
Parts of Compartments 78 & 79, Hutan Simpan Bukit Slim, PerakProject figures
Profile data at a glance
Project overview
Prepare. Plant. Regenerate.
The licence identifies Liput Raya Sdn Bhd as the licence holder and Layang Kaji Sdn Bhd as project contractor. The latest company profile records approximately RM1.5 million in infrastructure expenditure across the 7.5 km route from the main road, including bridge and access improvements.
For Phase 1 at Petak 3, 60 hectares were recorded as completed as at December 2025, while 40 hectares remained affected by rocky terrain. Phase 2 at Petak 4 was awaiting approval when the profile was prepared.
Nursery preparation and planting activities are documented from October 2025 through January 2026. The project also includes MC&I audit work, town halls and access-road settlement engagement with Pos Bersih, Orang Asli participation and school-focused ESG sponsorships.
Key highlights
Project priorities
- 01Timber harvesting and site preparation
- 02Forest plantation development
- 03Access-road, bridge and infrastructure improvement
- 04Nursery, seedling preparation and planting
- 05MC&I audit in progress
- 06Pos Bersih and Orang Asli engagement
- 07ESG and school sponsorship programmes
Scope of work
Activities on the ground
Site Preparation
Timber harvesting and preparation of plantation work areas.
Infrastructure
Improvement of the 7.5 km access route, bridges and supporting infrastructure.
Nursery Development
Nursery establishment, seedling preparation and planting readiness.
Plantation Development
Planting and progress activities across approved phases and work areas.
Community & ESG
Engagement with Pos Bersih, Orang Asli participation and school sponsorship programmes.
Compliance
Field documentation and ongoing MC&I audit activities.